The construction of a new sports pavilion that meets the participation demands and sporting clubs needs.
The Melrose Park change rooms and amenities are at the end of their useful life. Designs have been developed in consultation with the Melrose Football Club. The new sports pavilion building will address the identified amenity deficiencies such as lack of female change facilities, additional accessible public toilets, storage and community space with canteen facilities.
The NSW Government is providing $350,000 through an election commitment towards female friendly facilities. Council has been successful in securing $257,000 through Stronger Country Communities program round 4 for the project while Melrose Football Club is also contributing to the project.
Due the damaged caused to the existing building from fire, it was demolished. Temporary facilities have been funded through collaboration between the Melrose Football Club, Albury Wodonga Football Association and AlburyCity.
6 September 2024
The construction work is complete, and contractor demobilised. Surrounding area has been seeded.
18 August 2024
Building construction is nearing completion. Internal fit out is in the final stages while perimeter concrete works are well underway.
2 August 2024
5 July 2024
Soffit linings, suspended ceilings and tiling are completed. Joinery, toilet fit out and internal painting has commenced.
7 June 2024
24 May 2024
Blockwork and roofing are nearing completion. Guttering is attached and work has commenced on the underside of the roof. Internal works continue.
10 May 2024
Blockwork and service installation continues. Roof work commenced this week.
03 May 2024
19 April 2024
Internal blockwork continues.
5 April 2024
Framework construction is complete with internal blockwork underway.
29 March 2024
The steel framework has arrived on site. Installation has commenced.
1 March 2024
16 February 2024
Excavation and formwork underway for the raft slab
9 February 2024
Underground servicing is underway prior to preparing formwork for the raft slab.
26 January 2024
On-ground works have commenced on the new sport pavilion.
1 December 2023
At the Council meeting held on 27 November 2023, Council accepted the tender from Premier Building Construction Pty Ltd (PBC) for the construction of the Melrose Park Sports Pavilion. Construction is scheduled to commence in early 2024.
18 August 2023
After a lengthy detailed design process, the construction tender was uploaded to Tenderlink today. Tenders close 12 September 2023. Following assessment, a report will be presented to Council recommending a preferred contractor.
1 April 2022
There has been delays in progressing the detailed design of the building however procurement processes are well underway now and scheduled to close on 22 April 2022. Following the engagement of the design consultant, a review of timelines for detailed design completion, construction Tender awarded, construction commencement and project completion will be undertaken.
18 February 2022
Detailed design process is underway with construction ender due to be advertised in coming months.
29 October 2021
The Review of environmental factors has been determined. Work can now commence on detailed design
1 October 2021
The concept designs have been finalized with public exhibition process closed. The review of environmental factors is complete and awaiting determination.