Horseshoe Lagoon Boardwalk

The Horseshoe Boardwalk Lagoon project will improve the safety of the trail, as well as enhance the water scenery for our community to enjoy.

This project is complete and opened for Community use.

In 2021, the Yindyamarra Sculpture Walk and Wagirra Trail Realignment project saw two new 5km loops constructed. As part of the project, the need for the installation of a small section of boardwalk was identified.

This new boardwalk will remove the requirement for users to travel behind vehicles parked in the Riverina Highway car park, as they navigate the Yindyamarra Sculpture Walk.

In addition to the new boardwalk, we are constructing a small viewing platform, shelter, seating, and interpretative signage.

The project aims to create a safe and quiet space close to the water, to further enhance our community’s experience with one of our beautiful walking trails here in Albury.

Construction will commence in September 2023 for approximately five weeks, weather permitting. The car park and trail will remain open; however, some areas may be impacted during construction.

29 March 2024

Handrails installation is complete. The boardwalk and viewing platform are opened for community use.

HorseshoeBW 29-03

HorseshoeBW 29-03a

HorseshoeBW 29-03

15 March 2024

The handrails installation has commenced.

HorseshoeBW 15-03

HorseshoeBW 15-03a

9 February 2024

HorseshoeBW09-2

HorseshoeBW09-2a

HorseshoeBW09-2

26 January 2024

Boardwalk decking continues while the framework is nearing completion.

HorseshoeBW26-1a

HorseshoeBW26-1

HorseshoeBW26-1b

HorseshoeBW26-1c

22 December 2023

HorseshoeBW 22-12

HorseshoeBW 22-12a

HorseshoeBW 22-12b

8 December 2023

HorseshoeBW 08-12

HorseshoeBW 08-12a

HorseshoeBW 08-12b

1 December 2023

Screw pier installation continues while the framework for the boardwalk has commenced.

HorseshoeBW 01-12

HorseshoeBW 01-12a

24 November 2023

On-ground works commences with the installation of screw piers.

HorseshoeBW 24-11b

HorseshoeBW 24-11a

HorseshoeBW 24-11

20 October 2023

Off-site fabrication of the boardwalk is almost complete. Onsite works are set to commence soon.