Hovell Tree Park Public Toilets

The project involves the construction of new public toilets and a Changing Places facility.

The Hovell Tree Park public toilet and Changing Places facility is now complete and open for public use. The demolition of the old toilet block is scheduled to commence in January 2024.

The new Public Toilets will include six gender neutral toilets, one all abilities toilet with adult and child toilet and baby change table, and a Changing Places toilet.

Changing Places toilets are larger than standard accessible toilets, providing people with disability and high support needs access to suitable, safe, and private bathroom facilities.

The facilities include a height-adjustable adult-sized change table, a constant-charging ceiling track hoist system, a centrally-located peninsula toilet, additional circulation space more than standard accessible toilets, an automatic door with a clear opening of 950mm at a minimum, and a privacy screen.

Once complete, the Changing Places toilet at Hovell Tree Park will be accredited, receiving an official Statement of Compliance after inspection by a Changing Places Assessor.

It will also be registered on the Changing Places website, which gives people with disability and their carers access to a National Public Toilet Map to help them find local toilet facilities that meet their needs.

Changing Places toilets can be accessed using a Master Locksmiths Access Key (MLAK), which grants users entry 24-hours a day, 7 days a week.

More information to support those in our community with disability is available on our website here.


22 December 2023

Hovell Tree 22-12

Hovell Tree 22-12b

Hovell Tree 22-12a

1 December 2023

Minor internal fit-out works still need to be completed in the building. One operational the demolition of the old amenities building will commence.

Hovell Tree 01-12

Hovell Tree 01-12a

24 November 2023

Turf has been laid around the new public toilet building.

Hovell Tree 24-11a

Hovell Tree 24-11

17 November 2023

External concrete paths are complete. Minor internal fit-out and landscape works are still to be completed.

HovellToilet17-11

HovellToilet17-11a

HovellToilet17-11b

20 October 2023

Hovell Tree 20-10

Hovell Tree 20-10a

8 October 2023

Hovell Tree 8-10

Hovell Tree 8-10a

4 August 2023

Earthworks well underway.

Hovell Tree 04-08

21 July 2023

On-ground works commence.

Hovell Tree 21-07