The upgrade of sports field lighting and design development of priority buildings at Bunton Park
The Bunton Park Master Plan was developed to provide a long term strategic approach to improvements at Bunton Park. The Master plan was endorsed by Council in May 2020.
Funding has been allocated to commence the works from the master plan. Projects include:
8 June 2022
The remaining two light poles have been erected and power connected. The lights are scheduled to be switched on at Thursday nights training. The Club has also commenced the concrete work around the ground in preparation of installing new seating.
20 May 2022
Two of the light poles have been erected while the other two poles are prepared and scheduled to be erected next week. Note the size difference between the old light poles and the new light poles.
14 April 2022
The four light pole fountains have been installed as well as the concrete slab for the main switchboard.
1 April 2022
Preparation for installation of electrical conduits is underway. The bitumen has been saw cut while the dismantling of the old oval fencing has commenced. The small shelter has been removed to allow one of the light poles to be installed. A sample of the new picket fence has been installed
18 February 2022
Sports field lighting project - The foundation cages have been delivered to site while conduits have been installed across the ground.
1 October 2021
Sports field lighting project - Lighting design is complete and material quotations process underway
Building design work - A review of the sports club building continues
15 May 2021
Sports field lighting project - The lighting design is complete and provided to the club. An electrical plan is being developed
Building design work - A review of the sports club building continues
26 March 2021
Sports field lighting project - The lighting design for the site is being prepared which the electrical planning is underway. On-ground works will be included in the 2021-22 works program.
Building design work - a review of the old sports Club building is underway