Site Search

Building our City

Find out what current and planned works are happening in and around our city.

Updated: Thursday 6 October, 2022
  • Krautz Street – Maintenance grading/shoulder works are currently underway.
  • Road rehabilitation along Wyse Street/Thurgoona Street – Roundabout repairs commenced this week.
  • Road Resealing Program – Kerb and gutter works continue in Keating Court.
  • Mutsch Street – Kerb and gutter replacement is in progress, along with stormwater installation.
  • Pothole patching and road maintenance works are ongoing across the city.
  • Albury Riverside Precinct – Progress in the remaining landscape works has slowed due to high Murray River levels.
  • Thurgoona Oval Sporting Pavilion – Wall lining installation is nearing completion and tiling has commenced.
  • Ernest Grant Park – The contractor has proceeded with construction in the play space area. Works have experienced some delay due to inclement weather.
  • Keene Street Reconstruction – Road base was placed, with concrete work and landscaping almost complete for the entire project. The road base will be trimmed and sealed when weather permits.
  • Sewer Rehabilitation Program – Sewer main cleaning and rehabilitation works are continuing.
  • Borella Road Retaining Wall – We’re waiting for the water level in the stormwater channel to subside before resuming works.
  • National Foresters Grove Amenities – Roof and wall frame installation is scheduled to be completed this week. Roof installation is set to commence next week, weather permitting
  • Union Road Pedestrian Refuges – Union Road and Bralgon Street concreting works have started, however, inclement weather is causing some delays.

You can find out more about our Major Projects here

Image of works

.