Site Search

Building our City

Find out what current and planned works are happening in and around our city.

Updated Thursday 17 June, 2021
  • Thomas Street Rehabilitation pavement works have been completed with the exception of the asphalting which will be completed in the near future.
  • Construction of a footpath in Griffith Road is progressing well. Weather permitting, works will be finished next week.
  • Thurgoona Cycleway construction along Elizabeth Mitchell Drive has been slowed due to wet weather. Concrete works at Corrys Road roundabout will be completed this week.
  • Muntz Lane construction has commenced this week with services locating and drainage installation.
  • Kerr Road Reconstruction Stage 6 - the recent inclement weather has slowed the progress of the works significantly during the past week. However, the contractor has been progressing with bulk excavation and concrete works when possible.
  • Thurgoona Oval Sporting Pavilion - the builder is currently finalising the designs for the project. Whilst this occurs, we are working collaboratively on an accessibility issue identified by the team’s accessibility consultant.
  • Albury Waste Management Centre Construction and Demolition Waste Material Recovery Facility - the architect has produced a concept design for Council’s review. Whilst this occurs, the architect met with the building utility services engineers to begin work on the utility design packages.
  • Albury Regional Skate Park Facility - the recent inclement weather has slowed concrete pours to the various skate park elements dramatically. However, works are progressing when possible.
  • Keene Street Reconstruction - the recent inclement weather has slowed the progress of work this week. However, the pavement construction around the Keene Street and Andrews Street intersection is progressing in a manner as to not disrupt the usage of Alexandra Park.
  • Wagirra Trail Pedestrian Bridges - the contractor mobilised to site last week to recommence works. However, due to the inclement weather we are facing access issues to site.
  • Schubach Street Watermain - with commissioning now complete, all that remains is for the watermain to be cut over to the network and made live.
  • Jamieson & Mount Streets Footpath Construction - works are progressing well on the Jamieson Street section and are approximately 95% complete and the Mount Street section is completed.
  • Vickers Road Footpath Construction - works are progressing well and are approximately 90% complete.
  • Glenroy Area Footpath Construction - works are close to complete with only minor defects and omissions remaining.
  • Road Condition Survey - survey vehicles driving around Albury performing a visual condition assessment of our road network is taking a little longer than anticipated. However, we are still hoping to finalise the survey by early-July.
  • Albury Swim Centre Major Plant Replacement - the procurement of the major lead time items and design works is close to complete with a site measure performed this week in preparation for the installation of new plant. Installation works will commence once the materials have been processed through Australian Customs.

You can find out more about our major projects here.

Image of works

Never miss an update
account_circle
mail_outline
* We'll never share your email with third parties