Site Search

Equestrian Centre Improvements

This project involves the construction of covered stables, road works and camping area upgrades at the Albury Wodonga Equestrian Centre  Thurgoona .

Equestrian Centre improvements involve the addition of essential infrastructure that enhances the site for major events. Works include:

  • The construction of additional covered stables to address the shortfall for events
  • Internal roadways modifications to assist with the movement of large vehicles
  • Upgrade of event camping areas.

The project is funded through:

  • $287,063 - NSW Government Stronger County Communities Grant
  • $60,000 - AlburyCity
  • $60,000 - Albury Wodonga Equestrian Association

AWEC - Covered Yards design

21 November 2020

The project is now complete with the installation of the portable stables in the covered area.

AWEC 21-11

2 October 2020

The covered yard structure has been erected. Storm water tank has been connected with only electrical fit out to complete.

AWEC-Covered-Yards-02-10

AWEC-Covered-Yards-02-10a

25 September 2020

The roofing iron has been install on the structure this week with storm water connections to be completed. The portable yards have been purchased .

AWEC - Covered Yards 25-09

18 September 2020

In the last month the water tank and the gross pollutant trap have been installed. This week the the framework for the shed was erected with the roofing to be installed next week.

AWEC - Covered Yards 18-09

AWEC - Covered Yards 18-09a

14 August 2020

Storm water pipes have been laid  while water has been connected. The shed is scheduled to commence erection in the next few weeks

AWEC - Covered Yards 14-08

24 July 2020

Construction of the structure has commenced with the installation of the footings and rag bolt assemblies

AWEC - Covered Yards 24-07

19 June 2020

The earthworks are complete for the projects. Concrete footings are scheduled for July.

AWEC - Covered Yards 19-06

The earthworks for the covered yards commenced this week. The works are expected to take two weeks.

AWEC - 29-05