Site Search

Ernest Grant Park Play Space

The construction of a district level play space at Ernest Grant Park.

About this project

The Ernest Grant Master Plan was endorsed by Council in May 2020. One of the priority projects is the construction of a large high quality play space that encourages an active community of all ages and abilities.

The exciting project includes the following works:

  • All-inclusive playground
  • Skate Bowl
  • Pump track
  • Concrete Linking pathways
  • Shelters, Seating, and picnic settings
  • New 82 space car park on the western side of the park

16 December 2022

The majority of construction work is now complete. The last landscape elements and installation of playground softfall will be complete next week with the play space scheduled to be open prior to Christmas.

Ernest Grant New Skatepark Complete

Ernest 15-12

Ernest 15-12a

Ernest 15-12b

Ernest 15-12c

23 September 2022

concrete works continues on the bottom sections of the skate bowl. The concrete path construction is well underway linking the car park to the play area.  The shelter construction has commenced in the play area.

ErnGrantPS 23-09

ErnGrantPS 23-09a

9 September 2022

Works continues on the skate area while preparation starts on the linking pathway and play area.

ErnGrantPS 09-09a

ErnGrantPS 09-09

26 August 2022

Works continues on the skate area.

ErnGrantPS 26-08

12 August 2022

The shelter frame work has been installed while the first section of concrete has been completed.

ErnGrantPS 12-08b

ErnGrantPS 12-08a

ErnGrantPS 12-08

29  July 2022

Preparation and formwork commences on the skate area

ErnGrantPS 29-07a

ErnGrantPS 29-07

22  July 2022

Works continues on the car park and entry. Work has recommenced on the skate area and pump track.

ErnGrantPS 22-07b

ErnGrantPS 22-07

ErnGrantPS 22-07a

1 July 2022

The works has moved to the car park area whereby earthworks has commenced.

ErnGrantPS 01-07

ErnGrantPS 01-07a

17 June 2022

Works has slowed due to inclement weather. Drainage work continues on the skate park area.

ErnGrantPS 17-06

ErnGrantPS 17-06a

ErnGrantPS 17-06b

29 April 2022

Deliveries have started to arrive (storm water pits and pipes) while the tree removal in the car park area is complete. Service locations continue.

ErnGrantPS 29-04

ErnGrantPS 29-04a

ErnGrantPS 29-04b

14 April 2022

On-ground works has commenced with the erection of temporary fencing, construction of temporary pathway. and  installation of tree protection zones.

ErnGrantPS 14-04

ErnGrantPS 14-04a

18 February 2022

At the 14 February 2022 Council meeting Excell Gray Bruni were endorsed as the preferred contractor for the construction of the play space and car park. On ground works is scheduled to commence in April 2022.

1 October 2021

Tenders for the construction of the play space and carpark have been advertised and close 12 October 2021.

a

EGP- SK8

EGP- PS

EGP- CP

14 May 2021

The detailed design process is nearing completion. Funding has been successful through the NSW Government Every One Can Play Program.  Tender documentation is scheduled to commence later in 2021 for construction.

14 August 2020

PLAYCE have been engaged to undertake the detailed design of the play space while the AlburyCity design team is developing designs for the car park area